Method statement outlines materials and labor for safe suspended slab construction. All works must be approved by municipality before casting. Site Engineer must ensure all necessary approvals are received
Concrete pouring follows a sequence of preparation, forming, setting out, and finishing. Beam bottom formwork is placed first, followed by reinforcement installation. Formwork is fixed using props and leveling machine before concrete pouring
Formwork is surface and framing used to contain and shape wet concrete. Formwork should be rigid, watertight, braced and easy to remove. Design should consider safety risks and final concrete structure
Tremie is a watertight pipe with conical hopper above water level. Used to pour concrete underwater to prevent cement washout. Common applications include caissons, pilings, and monitoring wells