# How to create a portfolio and add projects

In this section, you will learn how to manage your portfolios:

* [Creating a portfolio](#create-potfolio)
* [Setting up a hierarchy](#add-portfolios-projects)
* [Editing multiple projects in a portfolio](#bulk-change)
* [Deleting a portfolio](#delete)

## Creating a portfolio {#create-potfolio}

To create a project portfolio:

1. Go to any page a portfolio can be created from:

   * In the left panel, select <svg xmlns="http://www.w3.org/2000/svg" width="18" height="18" fill="currentColor" aria-hidden="true" class="yc-icon nv-composite-bar__menu-icon"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><path fill="currentColor" fill-rule="evenodd" d="m8.879 4-.44-.44-.767-.767a1 1 0 0 0-.708-.293H6A1.5 1.5 0 0 0 4.5 4v5A1.5 1.5 0 0 0 6 10.5h7A1.5 1.5 0 0 0 14.5 9V5.5A1.5 1.5 0 0 0 13 4H8.879ZM6 1a3 3 0 0 0-3 3 3 3 0 0 0-3 3v5a3 3 0 0 0 3 3h7a3 3 0 0 0 3-3 3 3 0 0 0 3-3V5.5a3 3 0 0 0-3-3H9.5l-.768-.768A2.5 2.5 0 0 0 6.964 1H6ZM1.5 7A1.5 1.5 0 0 1 3 5.5V9a3 3 0 0 0 3 3h5.5a1.5 1.5 0 0 1-1.5 1.5H3A1.5 1.5 0 0 1 1.5 12V7Zm10.75 0a.75.75 0 0 0 0-1.5h-5.5a.75.75 0 0 0 0 1.5h5.5Z" clip-rule="evenodd"/></svg></svg> **Projects**, then click **Create** → **Portfolio**.
   * In the [list of portfolios and projects](https://yandex.com.tr/support/tracker/en/manager/my-projects.md), on the **Structure** tab, click **Create portfolio** under the list.
   * In the [list of portfolios and projects](https://yandex.com.tr/support/tracker/en/manager/my-projects.md), on the **List** tab, click **Create portfolio** under the list.

1. Enter a name for the portfolio, set the end date, and click **Create**.

1. On the **Description** tab, add information:

   * **Portfolio description**: What you are working on and what goals you want to achieve.
   * <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" aria-hidden="true" class="yc-icon"><svg xmlns="http://www.w3.org/2000/svg" viewBox="0 0 512 512"><path d="M67.508 468.467c-58.005-58.013-58.016-151.92 0-209.943l225.011-225.04c44.643-44.645 117.279-44.645 161.92 0 44.743 44.749 44.753 117.186 0 161.944l-189.465 189.49c-31.41 31.413-82.518 31.412-113.926.001-31.479-31.482-31.49-82.453 0-113.944L311.51 110.491c4.687-4.687 12.286-4.687 16.972 0l16.967 16.971c4.685 4.686 4.685 12.283 0 16.969L184.983 304.917c-12.724 12.724-12.73 33.328 0 46.058 12.696 12.697 33.356 12.699 46.054-.001l189.465-189.489c25.987-25.989 25.994-68.06.001-94.056-25.931-25.934-68.119-25.932-94.049 0l-225.01 225.039c-39.249 39.252-39.258 102.795-.001 142.057 39.285 39.29 102.885 39.287 142.162-.028A739446.174 739446.174 0 0 1 439.497 238.49c4.686-4.687 12.282-4.684 16.969.004l16.967 16.971c4.685 4.686 4.689 12.279.004 16.965a755654.128 755654.128 0 0 0-195.881 195.996c-58.034 58.092-152.004 58.093-210.048.041z"/></svg></svg> **File**: Add the portfolio files.
   * <svg xmlns="http://www.w3.org/2000/svg" xmlns:xlink="http://www.w3.org/1999/xlink" width="16" height="16" class="g-icon" fill="currentColor" stroke="none" aria-hidden="true"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><g clip-path="url(#svg-3uejtjjh__a)"><path fill="currentColor" fill-rule="evenodd" d="M10.257 4.2a.858.858 0 0 1-.86.274l-3.103-.776a2.81 2.81 0 0 0-2.796.876L1.242 7.152A3 3 0 0 0 .5 9.127V12a2 2 0 0 0 2 2h11a2 2 0 0 0 2-2V3.309a1.933 1.933 0 0 0-3.4-1.258l-1.31 1.528-.533.622ZM14 6.48V3.31a.433.433 0 0 0-.762-.282l-1.842 2.15a2.358 2.358 0 0 1-2.362.753L5.93 5.154a1.31 1.31 0 0 0-1.303.408L2.37 8.139a1.5 1.5 0 0 0-.37.988v.685l2.304-1.44a2.59 2.59 0 0 1 2.458-.155l1.923.888a1.578 1.578 0 0 0 1.777-.317l.22-.22 1.575-1.574A1.862 1.862 0 0 1 14 6.479ZM2 12c0 .277.226.501.5.501h11a.5.5 0 0 0 .5-.5V8.337a.4.4 0 0 0-.683-.283L11.523 9.85a3.078 3.078 0 0 1-3.466.618L6.134 9.58a1.09 1.09 0 0 0-1.035.066L2.352 11.36a.752.752 0 0 0-.352.637Z" clip-rule="evenodd"/></g><defs><clipPath id="svg-3uejtjjh__a"><path fill="currentColor" d="M0 0h16v16H0z"/></clipPath></defs></svg></svg> **Metric**: If you have a DataLens chart that tracks key portfolio metrics, embed it on the portfolio page. For more information about adding a metric, see [this](#add-metrics) guide.
   * <svg xmlns="http://www.w3.org/2000/svg" width="10" height="10" fill="currentColor" aria-hidden="true" class="yc-icon"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 14 14"><path fill="currentColor" fill-rule="evenodd" d="M7.873 13.125a.875.875 0 1 1-1.75 0V7.87H.875a.875.875 0 0 1 0-1.75h5.248V.874a.875.875 0 1 1 1.75 0V6.12h5.249a.875.875 0 0 1 0 1.751H7.873v5.255z" clip-rule="evenodd"/></svg></svg> **Link to project**: Add a link to a project.
   * <svg xmlns="http://www.w3.org/2000/svg" xmlns:xlink="http://www.w3.org/1999/xlink" width="16" height="16" class="g-icon" fill="currentColor" stroke="none" aria-hidden="true"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><g fill="currentColor"><path d="m8 9.076.085-.107a.751.751 0 1 0-1.171-.937L5.438 9.877 5.03 9.47a.747.747 0 0 0-1.06 0 .75.75 0 0 0 0 1.06l.407.408.593.592a.75.75 0 0 0 1.116-.061l.522-.654h.001L8 9.074Z"/><path fill-rule="evenodd" d="M12 11a3 3 0 0 0 3-3V4a3 3 0 0 0-3-3H8a3 3 0 0 0-3 3v1H4a3 3 0 0 0-3 3v4a3 3 0 0 0 3 3h4a3 3 0 0 0 3-3v-1h1ZM4 6.5A1.5 1.5 0 0 0 2.5 8v4A1.5 1.5 0 0 0 4 13.5h4A1.5 1.5 0 0 0 9.5 12V8A1.498 1.498 0 0 0 8 6.5H4ZM13.5 4A1.5 1.5 0 0 0 12 2.5H8A1.5 1.5 0 0 0 6.5 4v1H8a3 3 0 0 1 3 3v1.5h1A1.498 1.498 0 0 0 13.5 8V4Z" clip-rule="evenodd"/></g></svg></svg> **Checklist**: Specify the portfolio's key milestones or goals. You can work with a portfolio checklist just like an issue checklist. For details, see [Creating a checklist](https://yandex.com.tr/support/tracker/en/user/checklist.md).

   * In the right panel, specify the portfolio parameters.

     {% cut "Description of portfolio parameters" %}
      * **Status**: Specify the current stage of the portfolio.
      * **Start date** and **Deadline**.
      * **Lead**, **Customers**, **Followers**, and **Participants**: Start typing the name or login of the employee and select a relevant option from the list.
      * **Included in the portfolio**: Specify the parent portfolio.
      * **Tags**: Add or select the tags that would make it easier to find the portfolio.

      {% endcut %}

By default, a new portfolio is available to all organization employees. [How to restrict access to a portfolio](https://yandex.com.tr/support/tracker/en/manager/portfolio-access.md)

## Copying a portfolio {#copy-portfolio}

To create a new portfolio based on an existing one, use the copy option.

1. Open the portfolio you want to copy.

1. In the top right corner, select <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" aria-hidden="true" class="yc-icon"><svg xmlns="http://www.w3.org/2000/svg" viewBox="0 0 16 16"><path fill-rule="evenodd" d="M14 6.125a1.874 1.874 0 1 1 .001 3.749A1.874 1.874 0 0 1 14 6.125zm-5.906 0a1.874 1.874 0 1 1 0 3.749 1.874 1.874 0 0 1 0-3.749zM2 6.125a1.874 1.874 0 1 1 .001 3.749A1.874 1.874 0 0 1 2 6.125z"/></svg></svg> **Actions** → <svg xmlns="http://www.w3.org/2000/svg" xmlns:xlink="http://www.w3.org/1999/xlink" width="16" height="16" class="g-icon" fill="currentColor" stroke="none" aria-hidden="true"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><path fill="currentColor" fill-rule="evenodd" d="M12 2.5H8A1.5 1.5 0 0 0 6.5 4v1H8a3 3 0 0 1 3 3v1.5h1A1.5 1.5 0 0 0 13.5 8V4A1.5 1.5 0 0 0 12 2.5ZM11 11h1a3 3 0 0 0 3-3V4a3 3 0 0 0-3-3H8a3 3 0 0 0-3 3v1H4a3 3 0 0 0-3 3v4a3 3 0 0 0 3 3h4a3 3 0 0 0 3-3v-1ZM4 6.5h4A1.5 1.5 0 0 1 9.5 8v4A1.5 1.5 0 0 1 8 13.5H4A1.5 1.5 0 0 1 2.5 12V8A1.5 1.5 0 0 1 4 6.5Z" clip-rule="evenodd"/></svg></svg> **Copy project portfolio**.

1. Configure the portfolio copy options:
    - Specify who will have access to the copied portfolio: **All employees** or **Members only**.
    - To copy the portfolio's files and attachments, enable the **Copy files and attachments** option.
    - To add the source portfolio's projects to the portfolio, enable the **Include same projects in portfolio** option.
    - To copy the values of the portfolio's main fields, enable the **Copy main field values** option.

1. If you selected the **Copy main field values** option, fill in the **Summary**, **Start date**, **Deadline**, and **Responsible** fields. By default, the field values will be copied from the source portfolio.

1. Click **Create copy**.

## Setting up a hierarchy {#add-portfolios-projects}

You can add a project or portfolio to several additional portfolios and work with it just like any other. If a project is worked on by several teams, it will appear in the portfolio tree and on the Gantt chart of each team.

### Adding a parent portfolio {#add-parent}

1. Go to the project or portfolio page and click the **Included in the portfolio** field in the right panel.

1. Select the portfolio type: main or additional.

   {% note info "" %}

   You can add a project or portfolio to one main portfolio and several additional ones, but no more than 40 in total, including the main one.

   {% endnote %}

1. Start typing the portfolio name and select the option you need from the list.
1. Click **Save**.

### Adding a nested portfolio or project {#add-nested}

1. Go to the portfolio page.

1. In the top right corner, click **Add** and select **Portfolio** or **Project**:

    {% list tabs %}

    - Create new

        1. Click **New**.
        1. Enter a name for the project or portfolio.
        1. In the **Deadline** field, specify the end date. By default, the end of the current quarter is set as the end date. If you do not know the end date yet, click <svg xmlns="http://www.w3.org/2000/svg" xmlns:xlink="http://www.w3.org/1999/xlink" width="16" height="16" class="g-icon" fill="currentColor" stroke="none" aria-hidden="true"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><path fill="currentColor" fill-rule="evenodd" d="M8 1.5a6.5 6.5 0 1 1-6.445 7.348.75.75 0 1 1 1.487-.194A5.001 5.001 0 1 0 4.43 4.5h1.32a.75.75 0 0 1 0 1.5h-3A.75.75 0 0 1 2 5.25v-3a.75.75 0 0 1 1.5 0v1.06A6.48 6.48 0 0 1 8 1.5Z" clip-rule="evenodd"/></svg></svg> to reset the value.
        1. Click **Create**.

      The current portfolio will become the main one for the new project or portfolio.

    - Add existing

        1. Click **Existing**.
        1. Start typing the project or portfolio name and select the option you need from the list.

       {% note info "" %}

       If the existing project or portfolio already has a main portfolio, the current portfolio will become an additional one for it.

       {% endnote %}

   {% endlist %}

## Bulk editing projects in a portfolio {#bulk-change}

To make changes to several projects from one portfolio at once:

1. In the left panel, select <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="none" viewBox="0 0 16 16"><path fill="currentColor" fill-rule="evenodd" d="m8.879 4-.44-.44-.767-.767a1 1 0 0 0-.708-.293H6A1.5 1.5 0 0 0 4.5 4v5A1.5 1.5 0 0 0 6 10.5h7A1.5 1.5 0 0 0 14.5 9V5.5A1.5 1.5 0 0 0 13 4H8.879ZM6 1a3 3 0 0 0-3 3 3 3 0 0 0-3 3v5a3 3 0 0 0 3 3h7a3 3 0 0 0 3-3 3 3 0 0 0 3-3V5.5a3 3 0 0 0-3-3H9.5l-.768-.768A2.5 2.5 0 0 0 6.964 1H6ZM1.5 7A1.5 1.5 0 0 1 3 5.5V9a3 3 0 0 0 3 3h5.5a1.5 1.5 0 0 1-1.5 1.5H3A1.5 1.5 0 0 1 1.5 12V7Zm10.75 0a.75.75 0 0 0 0-1.5h-5.5a.75.75 0 0 0 0 1.5h5.5Z" clip-rule="evenodd"/></svg> **Projects** and open the portfolio you need.
1. In the selected portfolio, go to the **Projects** tab.
1. Select <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" class="yc-checkbox__icon-svg yc-checkbox__icon-svg_type_tick" viewBox="0 0 12 10"><path d="m.49 5.385 1.644-1.644 4.385 4.385L4.874 9.77.49 5.385zm4.384 1.096L10.356 1 12 2.644 6.519 8.126 4.874 6.48v.001z"/></svg> next to the portfolios and projects you want to edit.

   To select all the listed portfolios and projects at once, select <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" class="yc-checkbox__icon-svg yc-checkbox__icon-svg_type_tick" viewBox="0 0 12 10"><path d="m.49 5.385 1.644-1.644 4.385 4.385L4.874 9.77.49 5.385zm4.384 1.096L10.356 1 12 2.644 6.519 8.126 4.874 6.48v.001z"/></svg> above the list.

1. Under the list of portfolios and projects, select the operation you need:

   * **Change status**: Select a status from the list.
   * **Assign a lead**: Enter a login or name in the search bar and select the user.
   * **Move to portfolio**: In the window that opens, select an existing portfolio or create a new one on the relevant tab. If one or several of the selected projects and portfolios already belong to another portfolio, this operation will remove them from the previous one and add them to the newly selected one.
   * <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" aria-hidden="true" class="yc-icon"><svg xmlns="http://www.w3.org/2000/svg" viewBox="0 0 16 16"><path fill-rule="evenodd" d="M14 6.125a1.874 1.874 0 1 1 .001 3.749A1.874 1.874 0 0 1 14 6.125zm-5.906 0a1.874 1.874 0 1 1 0 3.749 1.874 1.874 0 0 1 0-3.749zM2 6.125a1.874 1.874 0 1 1 .001 3.749A1.874 1.874 0 0 1 2 6.125z"/></svg></svg> → **Edit parameters**: In the window that opens, change the parameters you need and click **Apply**. If the fields you need are not in the list, add them by clicking **Edit parameter list**.
   * <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" aria-hidden="true" class="yc-icon"><svg xmlns="http://www.w3.org/2000/svg" viewBox="0 0 16 16"><path fill-rule="evenodd" d="M14 6.125a1.874 1.874 0 1 1 .001 3.749A1.874 1.874 0 0 1 14 6.125zm-5.906 0a1.874 1.874 0 1 1 0 3.749 1.874 1.874 0 0 1 0-3.749zM2 6.125a1.874 1.874 0 1 1 .001 3.749A1.874 1.874 0 0 1 2 6.125z"/></svg></svg> → **Delete**: Delete the selected projects and portfolios.

1. After the operation is complete, a notification will appear in the bottom right corner showing the number of portfolios and projects that were successfully changed.

## Deleting a portfolio {#delete}

{% note alert "" %}

A portfolio can be deleted by its author or the user specified in the **Lead** field.

{% endnote %}

To delete a portfolio:

1. In the left panel, select <svg xmlns="http://www.w3.org/2000/svg" width="18" height="18" fill="currentColor" aria-hidden="true" class="yc-icon nv-composite-bar__menu-icon"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><path fill="currentColor" fill-rule="evenodd" d="m8.879 4-.44-.44-.767-.767a1 1 0 0 0-.708-.293H6A1.5 1.5 0 0 0 4.5 4v5A1.5 1.5 0 0 0 6 10.5h7A1.5 1.5 0 0 0 14.5 9V5.5A1.5 1.5 0 0 0 13 4H8.879ZM6 1a3 3 0 0 0-3 3 3 3 0 0 0-3 3v5a3 3 0 0 0 3 3h7a3 3 0 0 0 3-3 3 3 0 0 0 3-3V5.5a3 3 0 0 0-3-3H9.5l-.768-.768A2.5 2.5 0 0 0 6.964 1H6ZM1.5 7A1.5 1.5 0 0 1 3 5.5V9a3 3 0 0 0 3 3h5.5a1.5 1.5 0 0 1-1.5 1.5H3A1.5 1.5 0 0 1 1.5 12V7Zm10.75 0a.75.75 0 0 0 0-1.5h-5.5a.75.75 0 0 0 0 1.5h5.5Z" clip-rule="evenodd"/></svg></svg> **Projects** or follow the link [https://tracker.yandex.com/pages/projects <svg xmlns="http://www.w3.org/2000/svg" xmlns:xlink="http://www.w3.org/1999/xlink" width="16" height="16" class="g-icon" fill="currentColor" stroke="none" aria-hidden="true"><svg xmlns="http://www.w3.org/2000/svg" fill="none" viewBox="0 0 16 16"><path fill="currentColor" fill-rule="evenodd" d="M10 1.5A.75.75 0 0 0 10 3h1.94L6.97 7.97a.75.75 0 0 0 1.06 1.06L13 4.06V6a.75.75 0 0 0 1.5 0V2.25a.75.75 0 0 0-.75-.75H10ZM7.5 3.25a.75.75 0 0 0-.75-.75H4.5a3 3 0 0 0-3 3v6a3 3 0 0 0 3 3h6a3 3 0 0 0 3-3V9.25a.75.75 0 0 0-1.5 0v2.25a1.5 1.5 0 0 1-1.5 1.5h-6A1.5 1.5 0 0 1 3 11.5v-6A1.5 1.5 0 0 1 4.5 4h2.25a.75.75 0 0 0 .75-.75Z" clip-rule="evenodd"/></svg></svg>](https://tracker.yandex.com/pages/projects) and open the portfolio page.

1. In the top right corner of the page, click <svg xmlns="http://www.w3.org/2000/svg" width="16" height="16" fill="currentColor" class="1bcf880d__svg-icon" viewBox="0.5 -0.5 16 16"><path d="M8.5 4a1.5 1.5 0 1 1 0-3 1.5 1.5 0 0 1 0 3zm0 5a1.5 1.5 0 1 1 0-3 1.5 1.5 0 0 1 0 3zm0 5a1.5 1.5 0 1 1 0-3 1.5 1.5 0 0 1 0 3z"/></svg> and select **Delete project portfolio**.