metadata:
  - name: generator
    content: Diplodoc Platform v5.57.3
  - property: og:type
    content: article
  - property: article:section
    content: Managing issues with an Agile board
  - property: og:title
    content: Burndown chart for tracking sprint progress
  - property: article:tag
    content: Instructions collection
alternate:
  - https://yandex.com.tr/support/tracker/en/manager/burndown-diagram.md
  - href: en/manager/burndown-diagram.md
    type: text/markdown
    title: Markdown version
  - href: ../llms.txt
    type: text/markdown
    title: llms.txt
---
> **Documentation Index:** Fetch the complete configuration index at https://yandex.com.tr/support/tracker/en/llms.txt


# Burndown chart for tracking sprint progress

Teams that work in short iterations, or sprints, use a burndown chart to track progress. In Yandex Tracker, the chart shows how the amount of work left decreases as issues are completed during a [sprint](https://yandex.com.tr/support/tracker/en/manager/create-agile-sprint.md). It helps you assess the team's workload and the progress of planned issues every day.

{% note warning "" %}

Burndown charts are available on **With backlog and sprints** boards. If you use a Basic board, enable a burndown chart and other Agile tools: [Enabling Agile tools](https://yandex.com.tr/support/tracker/en/manager/boards-instruments.md#add-backlog).

{% endnote %}

## Viewing a burndown chart {#burndown-work-tips}

To view a burndown chart, open a board **with a backlog and sprints** and go to the **Burn down chart** tab.

![](../_assets/diagram-burndown.png =750x){.border-yes}

The chart opens for the current sprint. The horizontal axis shows sprint days and the vertical axis shows the workload remaining in **Story Points**. A dashed line is the [planned convergence](#burndown-plan), while the blue line is the [actual convergence](#burndown-fact).

* Compare the actual convergence line with the planned convergence line to assess progress:
  - If the lines diverge only slightly, the team is likely to complete the sprint issues on time.
  - If the actual convergence line is above the planned one, progress is slower than planned.
  - If the actual convergence line is below the planned one, the team is completing issues faster than planned.

* To see how the remaining workload changed on a particular day, hover over the chart at the corresponding point. The pop-up shows which issues changed in Story Points. [How the actual convergence line is built](#burndown-fact)

  Changes are recorded at the beginning of the working day and compared with the previous day.

* To open sprint issues from the chart, click a point on the burndown chart. The pop-up is pinned, so you can click an issue name.

## How the chart is built {#restrictions}

Burndown charts are intended for teams that use Scrum and work in short iterations called sprints. [Learn more about Scrum](https://en.wikipedia.org/wiki/SCRUM)

You can build a burndown chart if you use sprints and estimate issue complexity in **Story Points**: [Planning a sprint](https://yandex.com.tr/support/tracker/en/manager/create-agile-sprint.md#planning).

Burndown charts are available only for the current and upcoming sprints.

### Planned convergence {#burndown-plan}

Planned convergence is an ideal line that shows a steady decrease in the planned workload in **Story Points** during a sprint. It is built according to the following rules:

* The line starts on the first sprint day at the total Story Points for all sprint issues. It then descends evenly to zero on the last day of the sprint.

* The line accounts for weekends. The workload does not decrease on weekends, so the chart has steps.

* The total Story Points are fixed at the moment a sprint starts. You specify them when [creating a sprint](https://yandex.com.tr/support/tracker/en/manager/create-agile-sprint.md#create_sprint).

* If issues are added to or removed from the sprint, the planned convergence line does not change.

### Actual convergence {#burndown-fact}

Actual convergence shows the real completion velocity for issues planned in a sprint. The chart is updated each new day according to the following rules:

* Story Points increase if new issues are added to the sprint after it starts.

* Story Points decrease if a sprint issue is closed with the **Resolved** resolution or removed from the sprint.

  {% note warning "" %}

  Story Points on the chart do not decrease if you close issues without specifying a resolution. [Learn more about resolutions](https://yandex.com.tr/support/tracker/en/manager/create-resolution.md)

  {% endnote %}

* The sprint workload can also change when issues are re-estimated.